Meridian Water - Ground Improvement (CMCs) for Bridge Abutment CFA Piling Platforms

Project Overview

Meridian Water is a major Enfield regeneration scheme involving the construction of four new bridges to improve access and unlock future development.

The works include ground improvement, reinforced piling platforms to provide a strong enough platform for Bachy Soletanches CFA piling rig.

Prework processing of client information

- Creation of setting out file using AutoCAD LISPCommand scripts (correlated pile reference number with corresponding location)

- CMC/Pile reverting schedule drawing produced to ensure no clashes with future services to be placed into the ground.

Source: Taylor Woodrow, Meridian Water: Installing the B1 bridge

Installation of CMC’s (Controlled modulus columns)

- Setting out of CMC's within position tolerances

- CMCs reverted 600mm below the invert level of proposed future services using a 20T excavator with an auger attachment to required depths.

- Post work surveys and processing for submission to main contractor.

Project showcase

Meridian Water - Ground Improvement (CMCs) for Bridge Abutment CFA Piling Platforms

Successful delivery of bridge pile mats on behalf of Cognition Land & Water, supported by 300 mm Controlled Modulus Columns for Bachy Soletanche’s CFA piling rigs.

Fournew bridges
600 mmthick 6F2 piling platforms
300 mmControlled Modulus Columns
Fullprogramme, survey and quality coordination
Project overview

Ground improvement for a major regeneration scheme

Meridian Water is a major Enfield regeneration scheme involving the construction of four new bridges to improve access and unlock future development.

The works include ground improvement, reinforced piling platforms to provide a strong enough platform for Bachy Soletanches CFA piling rig.

Meridian Water site works
Technical delivery

Survey-led planning and controlled installation

AutoCAD setting out information and CMC pile schedule drawings

Prework processing of client information

  • Creation of setting out file using AutoCAD LISPCommand scripts (correlated pile reference number with corresponding location)
  • CMC/Pile reverting schedule drawing produced to ensure no clashes with future services to be placed into the ground.
Controlled modulus column installation photographs

Installation of CMC’s (Controlled modulus columns)

  • Setting out of CMC's within position tolerances
  • CMCs reverted 600mm below the invert level of proposed future services using a 20T excavator with an auger attachment to required depths.
  • Post work surveys and processing for submission to main contractor.
Source: Taylor Woodrow, Meridian Water: Installing the B1 bridge